PROCESS

OUR PROCESS

We know how daunting a task it can seem to our clients. We believe the most important aspect of the custom home building process is that you have faith in and trust your builder. You’ve come to the right place. You will not be alone in this process. We have carefully selected and organized our team of professionals to make the process as easy and straightforward as possible. There are systems, staff and resources in place to guide you in the selection process and oversee every aspect of the project. We have intentionally structured our team to allow for layers of oversight so that no detail is overlooked. That is the beauty of building a custom home with Peavy Homes.

Consultation & Budgeting

Once you’ve decided a custom home is in your future, the first step is to set up a consultation. We will meet to discuss your requirements for the school district, homesite size, special needs, and budget. We will locate a homesite and then design to maximize the characteristics of that homesite.

Preliminary Design

A Pre-Construction Agreement will need to be executed and a deposit is required to begin the design phase. Deposits are non-refundable but will be credited toward the purchase price of your new home. A deposit covers a full set of plans, engineered foundation, and geotechnical reports on soil testing.

Design Development

We have a designer on staff to help you narrow down your design options. Allowances are set at levels that are typical for your home’s size & price. Keep in mind there will always be more (and less) expensive design choices. Throughout the design process, we typically discuss hundreds of design alternatives. If an item is not in the plans or specifications, it’s not in the contract price.

Contract Signing

Once you approve the architectural plans and the budget pricing, we are ready to sign the contract! Your Peavy Home sales professional will prepare paperwork to place your plan and homesite under contract. Once your paperwork is finalized, you are ready to hand it over to your lender.  Be sure to ask about our lender partner, who is familiar with our new home construction loan timelines. 

Selections & Estimating

The selection process is fun, with all the designer options available. Making timely selections is extremely important so the construction process is not disrupted. Once you’ve made your selections, our vendors will estimate pricing for you to compare to your allowances. Items will not be ordered until you approve them. Once work has commenced, any changes will result in a change order.

Construction Preparation

Once we start your home, your Construction Superintendent is your main contact. We want the Construction Superintendent to be aware of every detail on the job. Our website will have a login page set up just for you, where you can view construction stages and communicate with your builder and interior designer.

Construction Begins

It’s time to clear your lot. Once the foundation is poured, we wait through an inspection process. It’s exciting when framing starts! Then things really get moving with mechanicals, electrical, insulation, and drywall. You’ll see doors, trim, and cabinets installed. Next, the paint color you’ve chosen goes up and fit and finishes are added just in time for your builder “punch-out” and pass all final inspections.

On-Time Completion

Once we are near to completion, you will be assigned a final walkthrough. Your Construction Manager will demonstrate all the systems of the home to you and identify any items that still need to be corrected. Final paperwork will be sent to your lender. On closing day you’ll sign the paperwork and make it yours. Welcome Home!

Follow Through Promises Kept

Your new home comes with a Home Warranty, which includes a one year “bumper to bumper” coverage for specific defects in workmanship and materials, two year major mechanical & plumbing, and ten-year structural coverage thru StrucSure. When you have a warranty issue outside of the 30 day and 11 month warranty period all you have to do is go to the warranty section of your personal page on our website and input your items.

FREQUENTLY ASKED QUESTIONS

  • Where Does Peavy Home build New Homes?

    Currently Peavy Homes builds quality new construction in Waco, TX. We are currently building homes in the China Spring, Hewitt, Lorena, McGregor, Robinson, Waco, and Woodway areas located in McLennan County.

  • Will Peavy Homes build on My Lot?

    If you own a lot, Peavy Homes will be glad to meet with you and discuss a home plan we currently build or a custom project on your property.

  • Do You Have Homes Available Now?

    Absolutely! We build homes for speculative sales, in several communities in the area. We have homes in progress, near to complete, and also completed homes in inventory that are available to close in your time frame. Just let us know how quickly you need to move and we will find the home that's right for you.

  • Can Peavy Homes Help Me Find a Mortgage Broker?

    Peavy Homes has had the opportunity to work with the very best Mortgage Brokers in the area. In our initial consultation, we will assess your needs and make recommendations to match you with the appropriate professionals within our industry who can explain the Construction Loan process.

CONSTRUCTION PROCESS

Lot Clear Stage

Plan on meeting with the Construction Manager on the lot prior to clearing. You will want to discuss trees to be saved, excavation, slab height, dropped brick ledges, etc.

Foundation Stage

  • Set forms
  • Fill with dirt
  • Plumbing rough-in (pvc drain pipe)
  • Inspection
  • Final grade dirt (this makes the forms for the concrete beams)
  • Plumbing (water lines)
  • Inspection
  • Slab steel
  • Inspection
  • Complete forms
  • Pour slab


Not much client interaction is required at this stage. This is one of slowest parts of the project since multiple contractors are needed, most activities only take a day or two, and they are all dependent on the one before them. On the inspection days, nothing happens because we must wait until the inspection clears before we can proceed to the next task.

Framing Stage

This is the most exciting stage of the process. When the framing is complete, the cabinet supplier will measure the framing and finish designing the cabinets to fit. For this reason, we do not detail out the cabinets on the architectural plans. The contract price includes standard cabinets and any specialties we note in the specifications. If you know you will want some cabinet upgrades then we can give you an allowance for those at the contract stage. It is imperative that you finalize the cabinet details as quickly as possible. They typically take four to six weeks to build and they need to be installed immediately after drywall.

Mechanical Rough Stage

Plumbing top-out (piping installed in the frame)


HVAC rough (installation of furnaces and ductwork) – We go to great lengths in the design stage to make sure there are adequate spaces to run the ductwork for the HVAC system. However, we occasionally have to add a fur down or block-out to accommodate a duct when there is no other possible alternative. If this is the case, we will consult with you on possible solutions.


Electrical rough – You should coordinate with the Construction Manager and do a thorough walk through of the electrical fixture locations as soon as the electrician installs the electrical boxes in the framing. If you see a location of an electrical box that you don’t like, we can usually move them for a minimal charge as long as we don’t disrupt the electricians work flow and we can notify them before they pull the wires to the boxes. As with the HVAC, sometimes the electrical just won’t work as it is shown on the plan, and in that instance, we will coordinate with you to come up with a solution.


Low voltage (phone, TV, & stereo) & security wiring – Prior to the installation of low voltage wiring, the contractor will be glad to meet you on the job to go over you needs room by room.


Framing & mechanical inspections – This is a critical and time consuming part of the process. The government or third party inspector will inspect the home and note any deficient items or items that don’t meet code. At the same time, your Construction Manager will be inspecting the home for accuracy to the plans and specifications and quality issues. It’s imperative that we get everything right before we go on to the drywall stage. This process takes some time, and it will seem as if nothing is happening since we have multiple contractors coming to the job to correct small items. Once all items are corrected, the inspector will re-inspect (if required by government authority) to verify compliance.


Exterior Paint – We will want you to approve a paint sample before we paint the exterior.


Roof installation


Masonry installation – If you are using any special stone colors or patterns, we will want you to approve a sample before we start the work. If you are using stucco, we will need to get the paint color approved prior to painting.

Drywall Stage

  • Insulation
  • Insulation inspection (if required by government authority)
  • Hang drywall
  • Tape & float drywall
  • Texture – If there are any special textures, we will want you to approve a sample before we start the work.

Trim Stage

  • Set Cabinets
  • Install doors & trim – It’s a good idea to meet with your Construction Manager and the trim carpenter at this stage to go over closet layouts and any specialty trim work.
  • Install wood floors (if applicable)

Paint Stage

  • Interior paint – We will provide a sample of the paint and stain you have selected on the job for your approval prior to painting. The purpose of this is to make sure that the color you selected looks the way you expected. We will make up to two samples of each selection. If more samples are needed, the painter will assess a charge per sample to cover his expenses.
  • Install septic system (if applicable)
  • Install driveways and walks – It’s a good idea to meet with your Construction Manager when we layout the driveways and walks. It always looks different on the lot than it does on the plan.

Tile Stage

  • Tub & shower surrounds
  • Tile floors
  • Countertops
  • Backsplashes
  • Fireplace surrounds
  • Set-out Stage
  • Install plumbing fixtures
  • Install electrical fixtures
  • Install HVAC condensers & grilles
  • Install mirrors & shower doors
  • Sand, stain & seal wood floors (if applicable)
  • Install landscaping
  • Carpet Stage
  • Install carpet
  • Install pre-finished wood floors (if applicable)

Punch-Out Stage

  • The term “punch out” is used in our industry to describe the process of correcting all the deficient items in the home. Actually, punch out will occur on your home throughout the construction project. The reason we call this stage punch out is because everything is basically done at this point, but the home is obviously not ready to move into. As a homebuilder, keeping this punch out stage to a minimum is one of our biggest challenges.
  • Final inspections

Closing Stage

Final walk-through – Once the home is 99% complete, your Construction Manager will schedule a final walk-through with you. The purpose of this walk-through is to demonstrate all the systems of the home to you (though by now you are probably already familiar with most of them) and identify any items that still need to be corrected. This walk-through should occur a few days before closing, which will give us the time to correct the deficiencies. Our goal is to have zero defects at the time of closing. It doesn’t benefit either of us to close on a home with a large punch list since the items only get more difficult to correct once the home is occupied. However, there are typically a few incomplete items at closing due to backorders or other unforeseen circumstances. In this instance, we will make a list of the remaining items that we both agree on, sign it, and make it a part of the closing documents.